4 Preparations for Power-On Commissioning
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
29
4.6 Preparing for the Management System Power-On
Commissioning
Prerequisites
The FusionModule1000 has been installed.
Preparations
Tools: none
Documents: monitoring component layout, ECC500 collector port layout, LAN switch port
layout, and management system initial configuration table
Skill requirement: weak-current engineer familiar with the management system
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Understand the layout of monitoring components by referring to the monitoring component
layout.
Step 2
Understand the connection relationship of the management system by referring to the
monitoring system networking diagram, ECC500 collector port layout diagram, and LAN
switch port layout diagram.
Step 3
Understand the initial configurations of the management system by referring to the
management system initial configuration table.
----End
4.7 Preparing for the Fire Extinguishing System Power-On
Commissioning
Prerequisites
The FusionModule1000 has been installed.
Preparations
Tools: none
Documents: fire extinguishing device layout diagram, fire extinguishing system conceptual
diagram
Skill requirement: fire extinguishing engineer