FusionModule1000B Water-Cooled IT Solution
Commissioning Guide
9 Commissioning Core Components
Issue 02 (2017-01-10)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
69
1.
(Optional) If an 8D ATS is configured, go to
9.1.1.1 (Optional) Commissioning the 8D
2.
After the ATS is commissioned, go to
Step 3
Switch on the SPD circuit breaker in the PDC to power on the SPD. The SPD indicators
become steady green.
Step 4
Commission monitoring devices in the PDC.
A PDC can be equipped with monitoring components such as an electricity meter or MDU. In certain
scenarios, no monitoring component is installed.
1.
(Optional) If a PD510 electricity meter is configured, go to
2.
(Optional) If an MDU is configured, go to
3.
(Optional) If no monitoring component is configured, go to
Step 5
(Optional) Commission the PD510 electricity meter.
1.
For details, see
9.1.1.2 (Optional) Commissioning the PD510 Electricity Meter
2.
After ensuring that the electricity meter works properly, go to
Step 6
(Optional) Commission the MDU.
1.
For details, see
9.1.1.3 (Optional) Commissioning the MDU
2.
After ensuring that the MDU works properly, go to
Step 7
Switch on the output circuit breakers in the PDC level by level as required to supply power to
downstream equipment.
----End
9.1.1.1 (Optional) Commissioning the 8D ATS
Prerequisites
You have powered on the 8D ATS.
Preparations
Tool: multimeter
Documents: documents delivered with the 8D ATS, 8D ATS initial configuration table, power
supply and distribution system diagram
Skill requirement: power distribution system engineer
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Check whether any alarm is displayed on the 8D ATS controller. If an alarm is displayed,
clear the alarm by following instructions in the delivered documents.
Step 2
Verify 8D ATS configurations by referring to the 8D ATS initial configuration table and
documents delivered with the 8D ATS.