TIP
You can choose either of the following methods to quickly view the progress and status of the MBTS
commissioning:
l
Click the table heading field of the task list to sort the commissioning tasks.
l
Click next to the table heading field of the task list to set the filtering condition. The task list displays
only the tasks that meet the filtering condition. If no filtering condition is set, the list of commissioning
tasks displays all the tasks that you are authorized to view.
Select a field in the task list, click , and then select
Custom
from the drop-down list. Set the filtering
condition in the displayed dialog box.
l
GBTS commissioning status (
GBTS List
area): The statuses of commissioning tasks are
displayed in
Status
. The progress of the current task is displayed in
Current Phase
. The
details of each stage under each status are displayed in
Description
.
l
NodeB commissioning status (
NodeB List
area): The statuses of commissioning tasks are
displayed in
Status
. The progress of the current task is displayed in
Current Phase
. The
details of each stage under each status are displayed in
Description
.
For example, when a commissioning task is in the
state (that is, the commissioning is being
performed), the operations such as version download, software upgrade, and configuration file
upgrade are performed.
For details about each status, see
.
Table 4-5
Description of the commissioning statuses
Status
Description
Start the MBTS commissioning task.
The commissioning is abnormal. View the alarm information, and then
handle alarms and perform fault diagnosis and alarm in time. For
details, see
.
Pay attention to the commissioning. For example, an exception occurs
in a certain procedure, which does not affect the commissioning and
does not need to be handled.
Manually intervene the commissioning of GBTS transmission. For
details, see
4.4 Manually Intervening the MBTS Transmission
.
No operation needs to be performed. The commissioning is being
performed normally.
Confirm whether to complete the commissioning. For details, see
Confirming the Completion of MBTS Commissioning
The commissioning is complete without errors. Obtain and archive the
commissioning report. For details, see
----End
3900 Series Multi-Mode Base Station
Commissioning Guide
4 Commissioning the MBTS in GU Mode on the M2000
Issue 02 (2010-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4-17