5.1 Procedure for MBTS Commissioning in GL or UL Mode
on the M2000
You can commission a base station in GL or UL mode on the M2000 in a central equipment
room, including upgrading software and configuring data, monitoring alarms, and obtaining the
commissioning report.
Prerequisite
Before you commission the MBTS, the MBTS, RNC, and M2000 must meet following
requirements:
l
The MBTS hardware such as the cabinets, cables, antenna system, and auxiliary devices,
is installed and passes the installation check. The MBTS is powered on and passes the
power-on check.
l
The controller hardware is installed and commissioned, and the system works properly.
The negotiation data of the MBTS to be commissioned is configured and recorded.
l
The M2000 is commissioned, it is connected to the corresponding controller, and the
configuration synchronization is completed.
In addition, the following requirements should be met:
l
Check that the network is normal.
l
The data configuration file and target version software package that map the mode of the
base station to be commissioned are ready. If a GBTS is to be commissioned, the data
configuration file and target version software package must be uploaded to the BSC.
l
The GBTS is activated using the
ACT BTS
command if one mode of an MBTS is GBTS.
Commissioning Flowchart
shows the procedure for remotely commissioning an MBTS in GL or UL mode on
the M2000.
3900 Series Multi-Mode Base Station
Commissioning Guide
5 Commissioning the MBTS in GL or UL Mode on the
M2000
Issue 02 (2010-07-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5-3