Verifying Line Connection
Touch the red multimeter lead to the line/hot connection and touch the black lead to the
ground lug. The meter should display a voltage verifying the presence of 230 VAC.
Verifying Neutral Connection
Touch the red multimeter lead to the neutral connection and touch the black lead to the ground
lug. The voltage value should not exceed 5 VAC.
Verifying Operating Voltage
Touch the red multimeter lead to the line/hot connection and touch the black lead to the
neutral. The meter should display a voltage value of 230 VAC ± 10%.
NOTE
All panel locks need to be in the lock position in order for rack to be properly grounded.
NOTE
Shown is the locked position, which
provides ground to the panel.
NOTE
After confirming line and neutral connections and the operating voltage is within the
specified range, power up the Vertex Edge® and check the operating voltage again to assure
the voltage under load is within the specified range for safe operation.
Vertex Edge Transformer Installation
The directions and diagrams enclosed herein are intended to illustrate the proper installation
and wiring of transformers designed to step-down or step-up site voltage to proper levels for
Vertex Edge System
36
User Manual
Summary of Contents for Vertex Edge
Page 1: ...Vertex Edge 72 POINT CONTINUOUS MONITOR ...
Page 2: ......
Page 6: ......
Page 19: ...Chemcassette 1 Chemcassette directional flow Vertex Edge System 18 User Manual ...
Page 29: ...Installation Drawings Vertex Edge System 28 User Manual ...
Page 46: ......
Page 59: ...Vertex Edge System 58 User Manual ...
Page 63: ...Vertex Edge System 62 User Manual ...
Page 69: ...Vertex Edge System 68 User Manual ...
Page 91: ...Vertex Edge System 90 User Manual ...
Page 96: ...Vertex Edge System 95 User Manual ...
Page 98: ...1 Main power ON OFF switch 2 Analyzer power switches Vertex Edge System 97 User Manual ...
Page 165: ... September 2021 1998 2002_EN_RevA1_VertexEdge_UserManual Vertex Edge System 164 User Manual ...