GREE Photovoltaic Direct-driven Inverter Multi VRF Units
21
1.4 Onsite Review of Design Drawing
Installation personnel must carefully read and understand the design scheme and drawings
provided by engineering designers, and prepare detailed and feasible construction organization design
after reviewing the onsite status.
The following aspects of working drawing must be reviewed:
(1) The loads of indoor and ODUs must match. The gross rated capacity of the IDU should be set to
a value that is 50% to 135% of the rated capacity of the ODU. In actual conditions, if the capacity
of concurrently operating IDUs exceeds 100% of the rated capacity of the ODU, the air
conditioning system fails to meet the requirement. Note: Configuration in excess of the capacity
of the IDUs can affect the comfort for users. The more the excess is, the lower the adjustment
capacity of an air conditioning unit will be. When the capacity exceeds 135% of the configured
value, the system reliability can be affected. Therefore, relevant regulations on capacity limit
must be strictly followed.
(2) The difference of level between an ODU and an IDU, and that between IDUs must be set within
the designed range.
(3) Pipe bend for trapped oil is required for air pipe riser in the unit to ensure normal circulation in
the unit lubricating system.
(4) The pipe diameter and manifold type in the cooling system must meet relevant technical
specifications.
(5) The drainage method of unit condensate water must be reasonable; the pipeline slope must
follow the design requirement of unit.
(6) The air duct direction and air flow are reasonably organized.
(7) The configuration specifications, type, and control method of power cables should meet the
design requirement of unit.
(8) The arrangement, total length, and control method of control line should meet the design
requirement of unit.
NOTICE
! Engineering construction personnel must strictly abide by the design drawings. If any
design cannot be implemented during construction and needs to be modified, contact the designer first
for approval and prepare a written document, that is, the design modification record.
Summary of Contents for GMV5 Series
Page 202: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 198 Troubleshooting ...
Page 253: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 249 Troubleshooting ...
Page 256: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 252 Troubleshooting ...
Page 262: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 258 Troubleshooting ...
Page 274: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 270 2 Check oil balancer ...
Page 287: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 283 ...
Page 321: ...JF00303868 ...