GREE Photovoltaic Direct-driven Inverter Multi VRF Units
132
B. If the system selects the heating mode, the main board is displayed as follows:
Progress
Commissioning Code
Progress Code
Status Code
Meaning
LED1
LED2
LED3
Code Display Status Code Display Status
Code
Display Status
16_Heating
commissioning
operation
db
On
16
On
AH
On
The system is in
heating-mode
commissioning operation
(the system automatically
selects the
commissioning operation
mode without needing
manual settings).
db
On
16
On
Corresponding
fault code
On
A fault occurs on the
heating-mode
commissioning operation.
db
On
16
On
J0
On
A fault occurs on other
modules during the
heating-mode
commissioning operation.
db
On
16
On
U9
On
A fault occurs on ODU
pipes.
db
On
16
On
XXXX/U8
On
The system detects pipe
failure of IDU. "XXXX"
indicates the project
number of the faulty IDU.
The fault code "U8" is
displayed after three
seconds. For example, if
a U8 fault occurs on IDU
100, LED3 will circularly
display "01", "00" (two
seconds later), and "U8"
(two seconds later).
Step 18: If no exception occurs when the unit continuously operates for 60 minutes, the system
automatically confirms commissioning completion, stops the entire unit, and restores the standby status.
The main board is displayed as follows:
Progress
Commissioning Code
Progress Code
Status Code
Meaning
LED1
LED2
LED3
Code Display Status Code Display Status Code Display Status
17_Commissioning
completion status
01~04
On
OF
On
OF
On
The unit has completed
commissioning and in
standby status. LED1
displays the module address;
LED2 and LED3 display "OF".
Step 19: After unit commissioning is completed, set unit functions according to the actual
engineering requirements on functions. For details about the setting method, refer to the "System
Function Setting Method" part. Skip this step if there are not special requirements.
Step 20: Deliver the unit for use and let users know the precautions.
(2) Commissioning Through the Commissioning Software
Step 1: Install commissioning software to the computer and connect monitoring communication
cables (for details about the operation method, see the "GREE Central Air Conditioning Commissioning
Software" section).
Summary of Contents for GMV5 Series
Page 202: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 198 Troubleshooting ...
Page 253: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 249 Troubleshooting ...
Page 256: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 252 Troubleshooting ...
Page 262: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 258 Troubleshooting ...
Page 274: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 270 2 Check oil balancer ...
Page 287: ...GREE Photovoltaic Direct driven Inverter Multi VRF Units 283 ...
Page 321: ...JF00303868 ...