Ceiling feed pole kit consists of a two-part vertical channel and two bottom brackets.
Ceiling feed pole installation on Above and Below Power troughs is identical. Above
trough is illustrated. Ceiling feed harness has already been connected to the Power
Distribution Module and data / communication cables, hanging from the ceiling, enter
designated Power trough through its grommet.
STEP 1: Secure bottom brackets to the bottom of the extruded pole with four supplied
screws as illustrated.
STEP 2: Organize data / communication cables and the ceiling feed metal conduit within
the pole and snap the pole cover closed.
STEP 3: Insert Ceiling feed junction box bracket into the top of the channel.
STEP 4: Position the assembled pole over the Power trough.
STEP 5: Mark and cut hole in the ceiling tile. Reinstall the ceiling tile and secure top of
the Ceiling feed pole to the ceiling tile grid.
STEP 6: Connect the Ceiling feed harness to the building power supply.
NOTE: There must be only one power feed entry into each cluster of harnesses.
WARNING! It is recommended that installation of the wiring system be made un-
der the supervision of a licensed electrician in accordance with applicable codes
and regulations. Connection to the building power supply must be done by a
licensed electrician. Do not connect or disconnect components while the system
is under load. Disconnect the main power before servicing or reconfi guration.
STEP 7: Slide a two-part Ceiling feed bezel over the pole and secure it to the ceiling tile
with supplied screws.
Ceiling feed and divider application on below worksurface Power Trough
Specify and install divider nominally 6” shorter than the worksurface. Divider brackets
remain in the same position.
Ceiling feed will only work on Back 2 Back applications with below worksurface through
and above worksurface trough.
Ceiling Feed
6