Cover trough’s installation consists of securing four brackets to work surfaces
immediately adjacent to storage towers. Brackets can be installed in two posi-
tions, which determine whether the trough cover is going to function as an Above
work surface or Below work surface trough cover.
Above work surface application.
STEP 1: Hold bracket against storage tower corner (panels A and B).
STEP 2: Secure four brackets by driving supplied screws into the work surfaces,
through two adjacent holes on the opposite end of the bracket as illustrated.
STEP: 3 Lower the Trough cover between the storage tower. The bottom of the
Trough will rest on top of the bracket.
Below work surface application.
STEP 4: Begin as above by holding the bracket against storage tower corner
(panels A and B).
STEP 5: Slide the bracket away from the tower until tip of the bracket C lines up
with end of the work surface (or storage panel B).
STEP 6: Secure four brackets by driving supplied screws into the work surfaces,
through two holes as illustrated.
STEP 7: Lower the Trough cover between the storage tower. The top of the
Trough will rest on the front tip of the bracket.
STEP 8: Scoop up power and data cables and secure them to the trough with
supplied rubber O ring
Back 2 Back Storage Tower Gap Filler Kit
1
4
2
5
3
B
B
A
C
7
8
6
Above worksurface
application.
Detail
Below worksurface
application.
Detail
NOT UL LISTED