D-700 MK3 User Manual Firmware V-16.8
- 181 -
The unit offers 3 ways of transferring the load from genset to mains and vice versa:
-transfer with interruption,
-no break transfer, (from genset to mains)
-soft transfer
This is the most conventional way of transferring the load between the genset and mains. There will be a
power interruption period during the transfer. Note that the program parameters
Mains Contactor Timer
and
Genset Contactor Timer
define the power interruption period.
Transfer from genset (or busbar) to mains:
-The generator (or busbar) contactor releases,
-The unit waits for Mains Contactor Timer
-The mains contactor is energized.
Transfer from mains to genset (or busbar):
-The mains contactor releases,
-The unit waits for Generator Contactor Timer
-The generator (or busbar) contactor is energized.
If this transfer method is used, it is advised to make an electrical
interlock between the two contactors to prevent an accidental
phase to phase short circuit.
31.1. TRANSFER WITH INTERRUPTION
31. LOAD TRANSFER MODES
Summary of Contents for D-700 MK3
Page 50: ...D 700 MK3 User Manual Firmware V 16 8 50 5 3 3 PHASE 3 WIRE DELTA 5 2 3 PHASE 4 WIRE STAR...
Page 64: ...D 700 MK3 User Manual Firmware V 16 8 64 7 2 MAINS SYNCHRONIZATION FUNCTIONALITY...
Page 65: ...D 700 MK3 User Manual Firmware V 16 8 65 7 3 SINGLE GENSET PARALLEL WITH MAINS FUNCT...
Page 66: ...D 700 MK3 User Manual Firmware V 16 8 66 7 4 DC GENSET FUNCTIONALITY...
Page 67: ...D 700 MK3 User Manual Firmware V 16 8 67 7 5 AMF FUNCTIONALITY...
Page 68: ...D 700 MK3 User Manual Firmware V 16 8 68 7 6 ATS FUNCTIONALITY...
Page 69: ...D 700 MK3 User Manual Firmware V 16 8 69 7 7 REMOTE START FUNCTIONALITY...
Page 70: ...D 700 MK3 User Manual Firmware V 16 8 70 7 8 ENGINE CONTROL FUNCTIONALITY...
Page 71: ...D 700 MK3 User Manual Firmware V 16 8 71 7 9 REMOTE DISPLAY PANEL FUNCTIONALITY...