2.11.2 External activation from optional PCB
Graph
Silent operation can also be activated from the optional PCB.
Silent operation will start when the contact on LNOP-COM is closed and will remain active as long as
the contact is closed. No field setting on the outdoor unit or by remote controller is required.
Silent operation will be ended when the contact is re-opened.
Use of the KRP58M enables the use of an external time clock.
Capacity priority
Setting
Same as with the automatic control, priority for capacity can be set.Prioirity for capacity will be
activated by changing field setting 26-0-03 in combination with the closed contact on KRP58M.
Exceptions
The silent operation will be overruled in the following conditions:
P
Pump down residual operation
P
Startup control
P
Defrost operation
P
Oil recovery
Sound reduction
Power supply connector
(on outdoor PCB X77A)
Output on X801M = 12VDC, 12mA
Maximum wire length = 100 meter
Transmission connector
(on outdoor PCB X6A)
Description
Mode
First
Code
Second Code
01
02
03
04
Silent Operation
16(26)
0
Factory
---
Capacity
priority
---
71
100
125
Sound reduction
4 dBA
4 dBA
5 dBA
ESIE05-03.book Page 25 Wednesday, April 6, 2005 4:09 PM
Summary of Contents for RZQ100B7W1B
Page 1: ...Service Manual ESIE05 03 RZQ71 125B8V3B RZQ100 140B7W1B Sky Air Inverter R 410A B series...
Page 2: ......
Page 10: ...ESIE05 03 viii Table of Contents 3 1 4 5...
Page 24: ...ESIE05 03 1 2 Part 1 System Outline 3 1 1 5...
Page 32: ...General Outline Outdoor Units ESIE05 03 1 10 Part 1 System Outline 3 1 1 4 5...
Page 42: ...Specifications ESIE05 03 1 20 Part 1 System Outline 3 1 1 4 5...
Page 56: ...Functional Diagrams ESIE05 03 1 34 Part 1 System Outline 3 1 1 4 5...
Page 58: ...ESIE05 03 1 36 Part 1 System Outline...
Page 70: ...Wiring Diagrams ESIE05 03 1 48 Part 1 System Outline 3 1 1 4 5...
Page 84: ...PCB Layout ESIE05 03 1 62 Part 1 System Outline 3 1 1 4 5...
Page 86: ...ESIE05 03 2 2 Part 2 Functional Description 3 1 2 5...
Page 110: ...General Functionality ESIE05 03 2 26 Part 2 Functional Description 3 1 2 4 5...
Page 150: ...ESIE05 03 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 188: ...Troubleshooting ESIE05 03 3 40 Part 3 Troubleshooting 3 1 3 4 5...
Page 264: ...Additional Checks for Troubleshooting ESIE05 03 3 116 Part 3 Troubleshooting 3 1 3 4 5...
Page 266: ...ESIE05 03 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 306: ...ESIE05 03 5 2 Part 5 Disassembly and Maintenance 3 1 5...