Field settings
ESIE05-03
4–16
Part 4 – Commissioning and Test Run
3
1
4
5
2.7
Setting the Centralized Group No.
When?
If you want to carry out centralized control with a central remote controller and a unified ON/OFF
controller, you have to set the group No. for each group with the remote controller.
Wired remote
controller
The illustration below shows the wired remote controller.
Setting
To set the “Centralized group No.”, proceed as follows:
SETTING
UNIT No.
GROUP
3
1
4
5
6
2
7
Unit N°
First Code N°
Second Code N°
Mode N°
Field set mode
Step
Action
1
Switch ON the power supply of the central remote controller, the unified ON/OFF control-
ler and the indoor unit(s).
2
Hold down the INSPECTION/TEST button for at least 4 s during normal mode to enter
the “Field setting mode”.
3
Press the TEMPERATURE CONTROL button until “Mode No.” “
00
” appears.
4
Press the INSPECTION/TEST button to inspect the group No. display.
5
Set the “Group No.” for each group by pressing the PROGRAMMING TIME button.
The “Group No.” rises in the order of 1—00, 1—01, ..., 1—15, 2—00, ..., 2—15, 3—00,
etc.
The unified ON/OFF controller however displays only the range of group numbers
selected by the switch for setting each address.
6
Press the CONFIRMATION button to enter the selected group No.
7
Press the INSPECTION/TEST button to return to normal mode.
ESIE05-03.book Page 16 Wednesday, April 6, 2005 4:09 PM
Summary of Contents for RZQ100B7W1B
Page 1: ...Service Manual ESIE05 03 RZQ71 125B8V3B RZQ100 140B7W1B Sky Air Inverter R 410A B series...
Page 2: ......
Page 10: ...ESIE05 03 viii Table of Contents 3 1 4 5...
Page 24: ...ESIE05 03 1 2 Part 1 System Outline 3 1 1 5...
Page 32: ...General Outline Outdoor Units ESIE05 03 1 10 Part 1 System Outline 3 1 1 4 5...
Page 42: ...Specifications ESIE05 03 1 20 Part 1 System Outline 3 1 1 4 5...
Page 56: ...Functional Diagrams ESIE05 03 1 34 Part 1 System Outline 3 1 1 4 5...
Page 58: ...ESIE05 03 1 36 Part 1 System Outline...
Page 70: ...Wiring Diagrams ESIE05 03 1 48 Part 1 System Outline 3 1 1 4 5...
Page 84: ...PCB Layout ESIE05 03 1 62 Part 1 System Outline 3 1 1 4 5...
Page 86: ...ESIE05 03 2 2 Part 2 Functional Description 3 1 2 5...
Page 110: ...General Functionality ESIE05 03 2 26 Part 2 Functional Description 3 1 2 4 5...
Page 150: ...ESIE05 03 3 2 Part 3 Troubleshooting 3 1 3 5...
Page 188: ...Troubleshooting ESIE05 03 3 40 Part 3 Troubleshooting 3 1 3 4 5...
Page 264: ...Additional Checks for Troubleshooting ESIE05 03 3 116 Part 3 Troubleshooting 3 1 3 4 5...
Page 266: ...ESIE05 03 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Page 306: ...ESIE05 03 5 2 Part 5 Disassembly and Maintenance 3 1 5...