Ground source heat pump
1. Switch off the Daikin Altherma GSHP via the user interface.
2. Remove the front panel, refer to the Daikin Altherma ground source heat pump Installer reference guide
(EGSQH10S18AA9W).
3. Remove the switch box cover, refer to the Daikin Altherma ground source heat pump Installer reference guide
(EGSQH10S18AA9W).
4. Unplug the connector X18A on the A9P PCB.
5. Measure the electrical conductivity between pin 2 and 4 of the connector on the flow switch; the value must be infinite.
6. Power the Daikin Altherma GSHP.
7. Activate “Installer level” on the user interface, refer to “Installer Level Settings” on the user interface are available in the
Installer Reference Guide, paragraph To access the most used commands.
8. Select Actuator test run A.7.4.
9. Activate the brine pump (A.7.4.I).
10. Measure the electrical conductivity between pin 2 and 4 of the connector on the flow switch; the value must be 0 Ohm (zero).
11. If the conductance measurements are not correct, the brine flow switch must be replaced, refer to
4.7. Brine pump M3P
Electrical check
Technical specification
Description
The brine pump M3P is a 3 speed pump.
The brine pump M3P circulates the brine in the
brine circuit.
Location
Piping diagram
Switch box
Unit
Check procedure
INSIDE OF UNIT - FACTORY INSTALLED
X77A
X28
F5U