28
Figure 3-12 Installation of the Wiring Box
5. Attach the main enclosure and the wiring box to the mounting
bracket with the
M6x18 screws
(6 pcs). (see
Figure 3-13
)
Tool required: No.3 Phillips head screwdriver, torque value of
4N.m (35.4in-lbs)
Figure 3-13 Secure the Main Enclosure and Wiring Box to the Bracket
Summary of Contents for SCA50KTL-DO/US-480
Page 2: ......
Page 6: ......
Page 53: ...47 Figure 3 24 Bypass Terminal option installed within the Standard wirebox ...
Page 139: ...133 Figure 10 1 CPS SCA50KTL kW and kVA derating curves of PV input voltage ...
Page 140: ...134 Figure 10 2 CPS SCA60KTL kW and kVA derating curves of PV input voltage ...
Page 141: ...135 Figure 10 2 CPS SCA60KTL Reactive Power Capability ...