104
5.
Set the grid standard. From the previous menu press
ESC
to return
to the
System Parameters
menu. If the display had been previously
returned to the main menu, follow the steps in (4) to access
System
Parameters
again. Select
System Parameters
, press
ENT
. Scroll
to
Grid Connection Rule
and press
ENT.
Use the arrow buttons to move up/down to the required grid standard.
Press
ENT
to select the required standard.
Grid Connection Rule
CA Rule-21/UL 1741 SA
HECO-ML
HECO-HM
IEEE1547
NONE
Figure 5-3 Set up Grid Standard
INSTRUCTION:
Check with your local utility company before selecting a grid standard.
If the inverter is operating with a wrong grid standard, the utility
company may cancel the interconnection agreement.
Placing the inverter into operation before the overall system complies
with the national rules and safety regulations of the application is not
permitted.
Summary of Contents for SCA50KTL-DO/US-480
Page 2: ......
Page 6: ......
Page 53: ...47 Figure 3 24 Bypass Terminal option installed within the Standard wirebox ...
Page 139: ...133 Figure 10 1 CPS SCA50KTL kW and kVA derating curves of PV input voltage ...
Page 140: ...134 Figure 10 2 CPS SCA60KTL kW and kVA derating curves of PV input voltage ...
Page 141: ...135 Figure 10 2 CPS SCA60KTL Reactive Power Capability ...