103
5.4
Commissioning Steps
Complete the list above before commissioning the inverter as follows:
1.
Turn on the AC circuit breaker.
2.
Turn
“ON” the external DC switch(s)/circuit breaker(s). Skip these two
steps if there are no switches or circuit breakers.
3.
Swi
tch the Inverter’s DC Switch to the “ON” position. When the energy
supplied by the PV array is sufficient, the LCD screen of inverter will light
up. The inverter will then start up with the message “sys checking”.
When the inverter completes
“
sys checking
”, the LCD will show the screen as
Figure 5-1 below.
Chint Power System
Initialization
Figure 5-1 System Checking Logo
4.
Setting Language. Press
ENT
to access the main menu, select
Setting
and press
ENT
.
The password is “1111”, using the arrow keys enter the
password and press
ENT
to access the next submenu. Select
System
Parameters
, press
ENT
. Scroll to
Setting Language,
press
ENT.
Then
select the desired language and press
ENT
.
Language setting
ENGLISH
CHINESE
Figure 5-2 Language Setting
Summary of Contents for SCA50KTL-DO/US-480
Page 2: ......
Page 6: ......
Page 53: ...47 Figure 3 24 Bypass Terminal option installed within the Standard wirebox ...
Page 139: ...133 Figure 10 1 CPS SCA50KTL kW and kVA derating curves of PV input voltage ...
Page 140: ...134 Figure 10 2 CPS SCA60KTL kW and kVA derating curves of PV input voltage ...
Page 141: ...135 Figure 10 2 CPS SCA60KTL Reactive Power Capability ...