M30 BOLSTERS STANDARD FOUNDATION INSTALLATION ONLY
With the Bolster on top of the road, secure to crane or on-site lift equipement. Then lift the entire Bolster into
the excavated foundation and level on leveling pad.
Once leveling of both bolsters is complete and matches your provided installation drawings pour concrete to
fill the foundations.
If needed, paint above surface Bolster areas that may have been chipped or exposed during offloading and
positioning in excavation with high quality outdoor paint
.
BOLSTER PLANNING & INSTALATION
!
Pay close attention to the dimensions on your drawings and any tolerances required!
Use laser level devices for accuracy.
Use a qualified heavy equipment operator or rigger to lift and set the Bolster in place.
Improper rigging may cause injury.
The center section of the Bolster should be filled first. This will minimize the po-
tential for shifting during the pouring process
.
!
Summary of Contents for Shield M30 Series
Page 33: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 33 ...
Page 42: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 42 ...
Page 43: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 43 ...
Page 44: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 44 ...
Page 45: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 45 ...
Page 46: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 46 ...
Page 47: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 47 ...
Page 48: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 48 ...
Page 53: ...1 800 944 4283 AutoGate Technical Support Mar 6 2019 53 ...