2 Chassis Enclosure
16
5. (Optional step) Add the front left and right handles to the
enclosure using five screws to secure each handle. Install a
thumbscrew through the bottom hole of each handle (see
Figure 2-7).
Note: These handles are optional and need only be installed when
mounting the system into a short rack. When mounting into a
deep rack, they are unnecessary and regular screws should be used
instead of thumbscrews.
Be aware that these handles are not to be used for lifting the system, they are
only to be used to slide the system within the rack.
6. With one person on either side (see the descriptive label on the
side of the enclosure), lift the enclosure and slide it into the
installed rails.
Warning! Be sure that the enclosure is empty of all blades, power sup-
plies, switches and management modules BEFORE lifting. These should
be installed AFTER the enclosure is mounted in the rack. Injury and dam-
age may occur if components are not removed from the rack prior to in-
stallation.
7. After pushing the enclosure all the way into the rack, use two
roundhead screws on each side of the server to lock it into place.
Figure 2-7. Attaching the Optional Handles
8. The enclosure is now securely installed in the rack (see Figure 2-8).
Summary of Contents for AB460 F1
Page 1: ...AB7000 Series User Guide ...
Page 14: ...xiv ...
Page 21: ...1 Document Description ...
Page 24: ...1 Document Description 4 ...
Page 25: ...2 Chassis Enclosure ...
Page 37: ...17 Figure 2 8 Enclosure Installed into Rack ...
Page 111: ...3 Server Blades Setup and Installation ...
Page 121: ...101 Figure 3 60 Card Installation ...
Page 171: ...151 4 DIMMs system memory 5 Airflow Deflector 6 CPU Heatsinks 7 Top Cover Item Description ...
Page 280: ...3 Server Blades Setup and Installation 260 ...
Page 281: ...4 Networking Switch Modules ...
Page 573: ...5 Acer Smart Blade Manager ...
Page 600: ...5 Acer Smart Blade Manager 580 ...
Page 601: ...Appendix A Troubleshooting ...
Page 616: ...Appendix A Troubleshooting 596 ...