Floor Screed Machine HD 50
14
www.utiform.com
departamento.té[email protected]
Tfno. + 34 96 570 29 82 Fax: + 34 96 570 29 83
3.4
Preparation for transport
•
Completely empty the mixing vessel.
•
Check the tire pressure.
•
Regulate the height of the coupling head.
•
Release the hand brake.
•
Couple the trailer to the traction vehicle
•
Raise the jockey wheel and then bend it.
•
Attach the brake safety cable.
•
Check the cover block, the closures, and the flap on the control panel.
•
Secure the locks, to protect against vandalism and theft.
•
For road transport the machine should have a working light bar.
3.5
Trailer Transport
For road transport the following should be taken into account:
• Respect the national traffic regulations of the country where the trailer is driven.
• Take documentation and traffic permit for the trailer.
3.6 Lorry
Transport
Use only one transport vehicle with sufficient load capacity for the total weight of the machine.
Immediately after loading the machine, stabilize it and attach it in such a way that it cannot come loose. Use
appropriate belts for this purpose, the blocks at the front of the machine, and activate the parking brake, depending
on the model of machine.
Secure any moving parts such as the top of the vessel and the transport pipes.
Transport of a machine without belts is prohibited.
Do not forget to remove the transport safety device key, before the next time the machine is transported.