Functions
2.17 Auxiliary Functions
SIPROTEC, 7SJ61, Manual
C53000-G1140-C210-1, Release date 02.2008
235
2.17.8
Commissioning Aids
Device data sent to a central or master computer system during test mode or commissioning can be influenced.
There are tools for testing the system interface and the binary inputs and outputs of the device.
Applications
• Test Mode
• Commissioning
Prerequisites
The following applies to the utilization of the commissioning aids as described below:
The device must be equipped with an interface.
The device has to be connected to a control center.
2.17.8.1 Description
Test Messages to the SCADA Interface during Test Operation
If the device is connected to a central or main computer system via the SCADA interface, then the information
that is transmitted can be influenced.
Depending on the type of protocol, all messages and measured values transferred to the central control system
can be identified with an added message "test operation"-bit while the device is being tested on site (test
mode). This identification prevents the messages from being incorrectly interpreted as resulting from an actual
power system disturbance or event. As another option, all messages and measured values normally trans-
ferred via the system interface can be blocked during the testing ("block data transmission").
Data transmission block can be accomplished by controlling binary inputs, by using the operating panel on the
device, or with a PC and DIGSI via the operator interface.
The SIPROTEC 4 System Manual describes in detail how to activate and deactivate test mode and blocked
data transmission.
Checking the System Interface
If the device features a system interface and uses it to communicate with the control center, the DIGSI device
operation can be used to test if messages are transmitted correctly.
A dialog box shows the display texts of all messages which were allocated to the system interface in the con-
figuration matrix. In another column of the dialog box you can specify a value for the messages you intend to
test (e.g. ON/OFF). After having entered password no. 6 (for hardware test menus) a message can be gener-
ated. The corresponding message is issued and can be read out either from the event log of the SIPROTEC 4
device or from the substation control system.
The procedure is described in detail in Chapter "Mounting and Commissioning".
Содержание SIPROTEC 7SJ61
Страница 368: ...Technical Data 4 22 Dimensions SIPROTEC 7SJ61 Manual C53000 G1140 C210 1 Release date 02 2008 368 ...
Страница 436: ...Appendix A 11 Measured Values SIPROTEC 7SJ61 Manual C53000 G1140 C210 1 Release date 02 2008 436 ...
Страница 438: ...Literature SIPROTEC 7SJ61 Manual C53000 G1140 C210 1 Release date 02 2008 438 ...
Страница 450: ...Glossary SIPROTEC 7SJ61 Manual C53000 G1140 C210 1 Release date 02 2008 450 ...
Страница 454: ...Index SIPROTEC 7SJ61 Manual C53000 G1140 C210 1 Release date 02 2008 454 ...