09/01/2014
06-03
19.
If installing panel-mounted radios, set-up the radio supports (side plate
mounts) at this time. The aft end of the radio supports will be riveted to the
instrument panel. Trim the forward ends as needed to clear Station 1.
Attach the forward end to the two diagonal frame tubes, under the
supports, with cushion clamps. Use the radio’s mount tray to set the width
of the supports and determine the panel opening. The exact details of the
installation will depend on the radios.
20.
Modify Panel Closeouts per
FIGURE 06-03C
.
Orientate cut FWD. Slip
over fuselage tubes and center. Transfer drill #30 to Panel Dash. Do
NOT
rivet to Dash until Final Assembly.
21.
Remove dash and place on a flat surface. Using contact cement spray
(3M SUPER 77 Multipurpose Spray Adhesive may be used) glue foam to
Dash up to, but not including both rivet hole lines (rivets will be placed
under the unglued foam and fabric in a later step) and allow to dry. Allow
overlap over the edges. Glue Panel Fabric over foam allowing about 1/4”
overlap on all edges.
IMPORTANT: Do NOT glue to Dash or foam beyond
the mounting rivet holes at this time.
22.
Un-cleco panel and drill all panel mounting holes in the panel to 5/16” to
allow for the rubber grommets (vibration isolators) to be installed. Do
NOT
drill the holes in the Panel Frame larger than #11.
23.
Remove Boot Cowl. Apply desired finish to inside and outside of Boot
Cowl. Prime and paint the outside. Prime and paint the inside. Fabric may
also be glued inside to the visible areas.
NOTE: If concerned about scratching the Boot Cowl, it is recommended to trial fit
and drill the windshield and the front trim strip windshield together with the
Boot Cowl before the finish is applied.
Refer to
WINDSHIELD
ASSEMBLY AND INSTALLATION.
The trial fit of the windshield is only
possible if the wings are installed. If you work carefully trial fit is not really
needed.
Содержание S-7S COURIER
Страница 26: ...RIVETS CROSS REFERENCE LIST...
Страница 28: ...1 T E 0703 TI ON 1 9 1 I I 8 T d 3 d d 0 3 OE O N t Z...
Страница 44: ...09 01 2014 01E 02 FINAL INSTALLATION For final installation refer to RUDDER PEDAL INSTALLATION...
Страница 119: ...09 01 2014 06 05 36 Check that the panel clears the fuselage frame to avoid vibration transmitted directly to the panel...
Страница 128: ......
Страница 129: ......
Страница 130: ......
Страница 131: ......
Страница 132: ......
Страница 157: ......
Страница 195: ......
Страница 196: ......
Страница 197: ......