Vertical Bracing
Depending on the static requirements,
horizontal forces can be transferred into
the structure using the vertical bracing.
This could be, e.g. transverse wind forc-
es acting on the climbing enclosure.
Mount Bracing Chains (8.1) with Bracing
Connectors LPS (8) crosswise on pro-
jecting Climbing Rail above the top slab
shoe.
Pre-tension Bracing Chain with a turn-
buckle:
– Oiled turnbuckle: hand-tightened.
– Non-oiled turnbuckle: hand-tightened
plus one complete turn (360°).
See PERI Design Information Section
3.3.1 and 3.4.5 "Lateral Bracing"
Components
8
Bracing Connector LPS
8.1
Bracing Chain LPS 5.0 m
B2 Planning the Units
LPS Screen Lightweight Climbing Enclosure
Instructions for Assembly and Use – Standard Configuration