D4 Moving by Crane
Moving Procedure
Version 1
1. Fold the guiding skids of the Slab
Shoe (10a) into the Climbing Rail (2)
and close. Climbing pawl remains de-
activated. (This step may have already
been done during preparations be-
tween Steps 1 and 2).
Version 2
1. Raise the climbing unit to the top
Climbing Shoes (10a) using the crane.
2. Insert Climbing Rail (2) into the top
Climbing Shoes (10a) using the Guide-
In Tool (98).
3. Close the guiding skids of the top Slab
Shoe. Climbing pawl remains deacti-
vated. (Fig. D4.03a)
Version 1 + 2
1. If necessary, deactivate pawls of the
bottom Slab Shoe (10c).
2. Raise climbing unit up to the planned
end position until the climbing pawls
of the middle Slab Shoe (10b) engage.
3. Lower climbing unit until the Spacers
are fully load-bearing on the climbing
pawls of the middle Slab Shoe (10b).
(Fig. D4.03 + D4.03a)
For operating the Slab Shoes, see Sec-
tion "Opening and Closing the Rail Guid-
ance Shoe" on Page 112 as well as Sec-
tion "Activating and Deactivating the
Climbing Pawl" on Page 113.
Components
2
Climbing Rail-2 LPS
10
Slab Shoe-2 LPS
98
Guide-in Tool
Fig. D4.03
Fig. D4.03a
LPS Screen Lightweight Climbing Enclosure
Instructions for Assembly and Use – Standard Configuration