D2 Operating the Slab Shoe
Opening and Closing the Rail
Guidance
The rail guidance (12) is the front part of
the Slab Shoe (10) or the Rail Guidance
Shoe LPS.
The climbing pawl (10.2) snaps into the
Spacer LPS 52 of the Climbing Rail.
The Threaded Bolts LPS DW 15 (10.1)
hold the guiding skids (10.3) in a closed
position. (Fig. D2.01 + D2.01a)
Opening the rail guidance:
1. Screw out Threaded Bolt LPS DW 15
(10.1).
2. Fold open guiding skid (10.3).
(Fig. D2.02a)
3. Proceed in the same way with the
other guiding skid. (Fig. D2.02b)
Opening the guiding skids facilitates in-
serting the Climbing Rail during climbing
and allows inserting the Climbing Rail
during initial assembly.
Closing the rail guidance:
1. Fold guiding skid (10.3) forwards.
2. Screw in Threaded Bolt LPS DW 15
(10.1) again.
3. Proceed in the same way with the
other guiding skid.
(Not shown)
Have both Threaded Bolts been screwed
in completely?
Components
10
Slab Anchor Shoe-2 LPS
10.1
Threaded Bolt LPS DW 15-2 LPS
10.2
Climbing Pawl
10.3
Folding Runners
10.4
Hole for Climbing Pawl
13.7
Threaded Anchor Plate DW 15 Ø
80 mm
13.9
KK Concrete Cone M24