SECTION 2 – USER RESPONSIBILITIES, MACHINE PREPARATION, AND INSPECTION
2-4
– JLG Lift–
2.3
PRE-START INSPECTION
The Pre-Start Inspection should include each of the following:
1. Cleanliness –
Check all surfaces for leakage (oil or bat
-
tery fluid) or foreign objects. Report this to the proper
maintenance personnel.
2. Structure
–
Inspect the machine structure for dents,
damage, weld or parent metal cracks or other discrep
-
ancies. Report this to the proper maintenance person
-
nel.
3. Decals and Placards
– Check all for cleanliness and
legibility. Ensure none of the decals and placards are
missing. Ensure all illegible decals and placards are
cleaned or replaced. (See Section 5-10 - DECAL
INSTALLATION)
4. Operation and Safety Manuals
– Ensure that a copy
of the Operation and Safety manual, AEM Safety Man
-
ual (ANSI markets only), and ANSI Manual of Responsi
-
bility (ANSI markets only) is enclosed in the weather
resistant storage container.
5. “Walk-Around” Inspection
– Refer to Figure 2-1. or
Figure 2-2. depending on model.
6. Battery –
Charge as required.
7. Hydraulic Oil
– Check the hydraulic oil level in the res
-
ervoir, add as required.
8. Accessories/Attachments
- Reference the Operation
and Safety Manual of each attachment or accessory
installed upon the machine for specific inspection,
operation, and maintenance instructions.
9. Function Check
– Once the “Walk-Around” Inspection
is complete, perform a functional check of all systems
in an area free of overhead and ground level obstruc
-
tions. Refer to Section 3 for more specific instructions
on the operation of each function.