Initial Energization
80
Controls Energization
Energizing the Control Panel will also energize the Meter and Protective Relay, enabling
addition commissioning verifications.
Addition Commissioning Verifications:
1. Proper Battery UPS Energization
2. Networking & SCADA Equipment Energization
3. Metering & Protection Relay Energization
Commissioning Steps:
1. Verify both automotive-style DC fuses are installed on the battery
2. Use a Multimeter (set to DC) to verify the presence of proper voltages at the
following locations on the UPS:
~24V DC (±0.1V, 23.9 - 24.1V) voltage on the top (input) terminals of the UPS
Содержание ClearSky Plus
Страница 16: ...Resources 16 West Terminations Side LV Cabinet West Terminations Side LV Cabinet Terminal Blocks 2 AWG Cu ...
Страница 21: ...Resources 21 ...
Страница 22: ...Resources 22 ...
Страница 28: ...Design Considerations 28 myPV ClearSky PLUS 25kV Termination Cabinet Door Swing ...
Страница 38: ...Receiving 38 Equipment is Wrapped Palletized Typically Equipment Delivery ...
Страница 45: ...Receiving 45 Top Fuse Mounting Hardware Three 3 MV Fuses Fully Assembled Installed ...
Страница 52: ...Electrical Terminations 52 LV Termination Cabinet ...
Страница 56: ...Network Integration 56 ...
Страница 64: ...Pre Energization Checks 64 View of Center Switching Cabinet Through Wire Glass Window ...
Страница 67: ...Pre Energization Checks 67 View of Three 3 PT Fuses Through Wire Glass Window ...
Страница 93: ...Operational Testing 93 Numbered Illustration of Protective Relay Indicators ...
Страница 102: ...Spare Parts 102 ...
Страница 103: ...Spare Parts 103 ...