Pre-Energization Checks
61
Grounding Verification
It is important that the myPV ClearSky PLUS be properly grounded to prevent any
transient voltages from not having a safe path to ground.
Due to the myPV ClearSky PLUS’s location on an equipment pad and grounding ring,
Solar-Ops recommends the maximum ohmic resistance between the device grounding
rod and the associated ground will be < 2Ω.
Both the Utility side and Solar side grounds should be verified.
Typical Utility Side & Solar Side Grounding Rod
MV Termination Verification
On both the Utility Side and Solar Side, all six (6) MV elbows should be be fully seated
on the inserts.
200A load-break connections are pushed on until the are fully seated and no “color ring”
is visible.
600A dead-break connections (e.g. “T-bodies”) are bolted on and need to be fully
seated and torqued per manufacturer instructions.
Содержание ClearSky Plus
Страница 16: ...Resources 16 West Terminations Side LV Cabinet West Terminations Side LV Cabinet Terminal Blocks 2 AWG Cu ...
Страница 21: ...Resources 21 ...
Страница 22: ...Resources 22 ...
Страница 28: ...Design Considerations 28 myPV ClearSky PLUS 25kV Termination Cabinet Door Swing ...
Страница 38: ...Receiving 38 Equipment is Wrapped Palletized Typically Equipment Delivery ...
Страница 45: ...Receiving 45 Top Fuse Mounting Hardware Three 3 MV Fuses Fully Assembled Installed ...
Страница 52: ...Electrical Terminations 52 LV Termination Cabinet ...
Страница 56: ...Network Integration 56 ...
Страница 64: ...Pre Energization Checks 64 View of Center Switching Cabinet Through Wire Glass Window ...
Страница 67: ...Pre Energization Checks 67 View of Three 3 PT Fuses Through Wire Glass Window ...
Страница 93: ...Operational Testing 93 Numbered Illustration of Protective Relay Indicators ...
Страница 102: ...Spare Parts 102 ...
Страница 103: ...Spare Parts 103 ...