6 Assembly: Bell-type tank design
Maschinenfabrik Reinhausen GmbH 2015
159
4349315/00 EN
VACUTAP® VR®
Drying the on-load tap-changer
1.
Connect pipe connections R and Q of on-load tap-changer head to the
kerosene vapor lead using one shared lead.
Figure 212: Shared lead
2.
Seal off unused pipe connections with a suitable blank cover.
Vapor-phase drying in the transformer tank
1.
Supply kerosene vapor at a temperature of around 90 °C. Keep this
temperature constant for 3 to 4 hours.
2.
Increase the kerosene vapor temperature by approx. 10 °C/hour to the
desired final temperature (125 °C maximum on the on-load tap-chang-
er).
3.
Vacuum dry on-load tap-changer at between 105 °C and maximum 125
°C for at least 50 hours.
4.
Residual pressure of no more than 10
-3
bar.
Closing kerosene drain plug
1.
Remove diverter switch insert [
2.
Close kerosene drain plug with extended socket wrench by turning
clockwise (tightening torque 20 Nm).
3.
Insert diverter switch insert [
6.9.2.4
6.9.2.5
Содержание VACUTAP VR
Страница 1: ...On Load Tap Changer VACUTAP VR Installation and Commissioning Instructions 4349315 00 EN ...
Страница 246: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 246 4349315 00 EN VACUTAP VR ...
Страница 248: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 248 4349315 00 EN VACUTAP VR ...
Страница 266: ......
Страница 267: ......