11 Commissioning transformer at installation site
Maschinenfabrik Reinhausen GmbH 2015
222
4349315/00 EN
VACUTAP® VR®
4.
NOTICE!
Switch on transformer. Once the transformer has been
switched on, ensure that the inrush current impulse has fully subsided
before undertaking an on-load tap change operation. The inrush current
impulses are usually a multiple of the transformer rated current and can
overload the on-load tap-changer during the diverter switch operation.
ð
After the transformer has been switched on and the inrush current im-
pulse has subsided, on-load tap-changer tap-change operations can be
performed both under no load and load conditions.
During all function checks and tests when commissioning, in addition to the
safety instructions in Chapter 2, also note the safety notice provided in the
chapter Electrical high voltage tests on the transformer [
Содержание VACUTAP VR
Страница 1: ...On Load Tap Changer VACUTAP VR Installation and Commissioning Instructions 4349315 00 EN ...
Страница 246: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 246 4349315 00 EN VACUTAP VR ...
Страница 248: ...14 Appendix Maschinenfabrik Reinhausen GmbH 2015 248 4349315 00 EN VACUTAP VR ...
Страница 266: ......
Страница 267: ......