Sheeter SVC 525C
95
Set-up, commissioning
Making the stationary mains connection
7.3.6
Checking the protective conductor connections
Check that all protective conductor connections that were disconnected for
transport are reconnected correctly.
Procedure:
Check this by visual inspection.
WARNING!
Disconnected protective conductor connections.
Non-observance could result in serious injury or death.
Reconnect all protective conductor connections that were disconnected
for transport.