11
Technical Manual
Kingspan SHE Control Panel TRZ Plus
2A and TRZ Plus Comfort
12/24999513
Installation
Disconnect the control panel from power supply (mains and battery), plug the spacer to the principal circuit control board,
plug the additional module to the extension ledge, create the desired connections and check, re-establish power supply
(mains and battery).
Check wind/rain detection function
No SHE and no malfunction signal, the green LED
OK
operating is shining. Press the switch Open at the vent switch, the
motor opens. Moisten the rain sensor surface of the weather detector, the drives close. If the vent switch has a display for
Open, it flashes. The ventilation function is blocked as long as a wind or rain alarm is pending. Activate SHE
- the drives
have to open during a pending wind or rain alarm (SHE has priority). To test the wind detection, a permanent air current has
to be detected at the wind wheel approx. 3 min (e.g. a hair dryer). Otherwise proceed for the checking as described above.
Check Alarm (SHE) and malfunction function
No SHE and no malfunction detection, green LED
OK
- operating - is shining. Activate SHE
. The closing contact at the
terminals 4 + 5 switches. The function is OK if the passage can be measured. Activate SHE Closed
, initial position, no
SHE-activation and no malfunction detection. Take off the battery fuse F3 to simulate a malfunction, Activation! Replace
fuse F3 back, control panel again in initial position, repeat complete bringing into service of the TRZ Plus 2A. No errors,
function is OK, system ready for operation.
2. SHE manual call point TRZ/RBH-Basic
integrated in the TRZ Plus front door. Not suitable for compact control panel 2A and 2A/M.
Possible Connections
LED-display
Extension ledge
Switch SHE-activation
SHE manual call point TRZ/RBH
Switch SHE Closed (no Reset)
OK
!
Installation
Disconnect power supply (mains and battery), mount additional module at the inside of the control panel door, plug the plug
to the extension ledge of the principal circuit control board or, if available, of the add. module TRZ/WRMAS, reconnect power
supply (mains and battery).
Function check
Proceed as indicated page 65, point “SHE man. call points“, repeat the complete bringing into service of the TRZ Plus, no
errors, function OK, system is ready for operation.