Page 41
Garden Building
Installation Guide
Product Code : TGBv6.1 / November 2011
The transom glazing bars need to be
installed next.
Start with any glazing bars that connect to
the 25° pitch ridge.
After removing the protective film from the
glazing bar under cladding slot the transom
glazing bar holes over the M5 x 25mm bolts
in the double bolt retainers located in the
ridge.
Repeat for the holes at the bottom of the
transom glazing bars which connect to the
M5 x 25mm bolts in the double bolt retainers
located in the eaves beam. Loosely thread
on the M5 flange nuts. Do not tighten at this
stage.
Repeat for any more transom glazing bars
that connect to the 25° pitch ridge.
Jack Rafters
The final set of glazing bars, the jack rafters
need to be fitted. The jack rafter glazing bars
have tops which are cut at an angle and
when in position will run perpendicular from
the eaves beam until they meet and attach
to the Georgian hip glazing bar.
Before attaching the jack rafter, slide the
jack rafter glazing bar under cladding down
and away from the top end of the jack rafter.
REMEMBER to remove the protective film.
If not already fitted, locate a domed bolt
(C9165) into the jack rafter bolt slot which is
located runs the entire length of the
Georgian hip bar. Locate the jack rafter arm
(C9166) onto the domed bolt and loosely
attach the M6 flange nut. Do not tighten.