Figure 3-58 Removing the sheet metals for transporting the compressor
NO TE
Put away the removed sheet metals so that you can reinstall them if the indoor unit is to
be transported again.
Step 2 Tighten the bolts with torque of 15 N•m.
----End
3.8 Installation Verification
Indoor Unit Installation Verification
After installing an indoor unit, check the components listed in the following table.
Table 3-14 Check items on the indoor unit installation
Check Item Expected Result
Cabinet
● The cooling system has good air tightness.
● The cabinet is installed properly, without any tilt.
● The cabinet is secured to the support by using bolts.
● The foreign matter inside the cabinet such as cable ties and
stubs is cleaned up.
Electric
heater
The electrical heater is secured.