-24-
Model G0841 (Mfd. Since 06/18)
Leveling
Leveling machinery helps precision components
remain straight and flat during the lifespan of the
machine. Components on an improperly leveled
machine may slowly twist due to the dynamic
loads placed on the machine during operation.
For accurate planing results and to prevent
warping or twisting of cast iron base,
machine MUST be leveled from side to side
and from front to back on both ends.
Re-check the machine 24 hours after
installation, two weeks after that, and then
annually to make sure it remains level.
To level machine:
1. Slide (4) leveling pads under (4) footings at
corners of machine, as shown in
Figure 17.
Make sure center of threaded hole in footing
aligns with center of leveling pad.
2. Insert (4) M16-1.5 x 75 hex bolts with (4) M16-
1.5 jam nuts into (4) threaded holes in foot-
ings, as shown in
Figure 17.
Hex Bolt
Jam Nut
Leveling Pad
Footing
Threaded
Hole
Figure 17. Leveling hardware orientation
(1 of 4).
— Insert forklift forks through slots on bottom
of machine (see
Figure 16). Slots are 36"
on center and accept forks up to 6" wide.
Figure 16. Example of lifting machine with
forklift.
5. Raise machine a couple of inches and check
balance of load. If using straps, have two
other people carefully steady machine to help
prevent it from swinging.
6. Raise machine enough to clear shipping pal-
let and carefully remove pallet.
7. Slowly lower machine into position.
Leveling
Содержание G0841
Страница 84: ......