25
Note: In Multi mode, the job/color/type display does not appear even if the
Plotter Prompts check box is turned on in the Plotter Settings dialog box in the
GAPlot32/GSPPlot program.
Job Status displays
Running
and
## % DONE
. (The percentage appears
only with OMEGA or GA version 6.2 or higher. See previous page.)
To pause the job while it is running, or to restart it, press F1.
If you send another job to the plotter, it will begin as soon as the current
jobs are done.
If a job does not start when running in multi mode
When running multiple jobs, the next job will not begin if one of the
following conditions occurs:
♦
a job clipped message appears
♦
a slew key was pressed
♦
the Cancel key was pressed
♦
a system error occurred
♦
the plotter was switched to Single, then back to Multi
If any of the above conditions occur, press F1 to start the job.
If you pressed F1 before sending a job to the plotter, it will begin as soon
as the plotter receives it, provided these conditions are met:
♦
The material is loaded and a tool is installed.
♦
A slew key was not pressed. (This is to prevent the plotter from
starting while the tool or material is being positioned.)
If you press a slew key between jobs, you must press the F1 key (Start-
Job) to start the next job.
Pausing, restarting, and canceling jobs
Pausing a job suspends it temporarily. You can pause a job by pressing
F1, Pause-Job. The plotter will stop at the next available break point.
After pause, you can look at your job by using the slew keys to move the
material. When you restart the job, the plotter repositions itself and starts
at the position where it left off.
Note: Once a job has begun, slewing will not affect the job. Moving the pinch
wheel lever terminates the job.