EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
©
Ericsson AB 2010
Commercial in confidence
33 (200)
3
Resources
The following equipment is required to carry out the tests described in this
document.
3.1
Documentation
The following documentation is required to commission the EDA 2530.
No.
Description
Code
Qty
1
This document – EDA 2530 Commissioning
Procedure for Cable and Wireless Access.
2/153 22-FGC 101
0239 Uen
1
2
The EDA 2530 Software and Firmware Release
Note for the release of the EDA 2530 being
commissioned.
1
3
Customer specific Configuration information i.e.
Floor Plan, EDA 2530 Rack Layout, EDA 2530
Subrack equipment allocations, Cable Running Out
Lists.
1
3.2
Tools
No.
Description
Code
Qty
1
Anti Static Wrist Strap and connection cable.
1
2
Anti Static bags for Slide in Units or Anti Static
containers.
As
required
3
Screwdrivers – Flat Blade and Crosshead.
2
4 Side
Cutters
1
5
Krone IDC Connection tool see picture
CWA013
2
6
Continuity Tester (Buzzer) for checking new cables.
1
7
T-Bar Unit Extraction Tool
151-2765/01
1
3.3
Test Equipment
Record details of the test equipment used on the Record of Test Equipment Form.
Approved equivalents may be used if the items specified are not available.