EDA 2530 Commissioning Procedure for Cable and Wireless Access
1/153 22-FGC 101 0239/2 Uen Rev J 2010-04-01
©
Ericsson AB 2010
Commercial in confidence
8 (200)
1.4
Static Sensitive Device Handling Precautions
Equipment referred to in this document contain static sensitive devices and
therefore an ESP wrist strap MUST be worn and connected to an ESP bonding point
at all times when handling slide-in-units and socketed devices (PROMS).
1.5
Optical Device Precautions
The EDA Subrack may be equipped with Optical Common Part Units containing
laser transmitters. Never look into a laser transmitter port or into a fibre optic cable.
1.6
Inspection/Cleaning Procedure For Optical Connectors
All optical fibre connectors will require inspection for damage and cleanliness.
1.7
Commissioning Test Records
The commissioning test records at the end of this document must be completed as
the commissioning progresses. A complete set of Test Records must be completed
for each EDA 2530 being commissioned. This should be retained on site for the
customer’s use if requested. Any items outstanding after the acceptance testing is
complete are to be listed in the Outstanding Items Summary at the end of this
document.
When all acceptance testing has been completed successfully, both the Ericsson
and Customer’s representatives must complete the Customer Acceptance Form at
the end of this document. If the Customer’s representative is not present on site
enter N/A (Not Available) for the Customer representative.