Commissioning Examples for the Power Protection Module
Object to be tested:
Testing the projected Power Protection Modules:
P>;
P<;
Pr>; and
Pr<.
Necessary means:
3-phase AC voltage source ;
3-phase AC current source; and
Timer.
Procedure – Testing the wiring:
•
Feed rated voltage and rated current to the measuring inputs of the relay.
•
Adjust the current pointers 30 degrees lagging to the voltage pointers.
•
The following measuring values have to be shown:
P=0.86 Pn;
Q=0.5 Qn; and
S=1 Sn.
If the measured values are shown with a negative (algebraic) sign, check
the wiring.
The examples shown within this chapter have to be carried out with the
tripping values and tripping delays that apply to the User's switchboard.
If the User is testing „greater than thresholds“ (e.g.: P>), start at 80% of the
tripping value and increase the object to be tested until the relay picks up.
In case the User is testing „less than thresholds“ (e.g.: P<), start at 120% of
the tripping value and reduce the object to be tested until the relay picks
up.
If the User is testing tripping delays of „greater than“ modules (e.g.: P>),
start a timer simultaneously with an abrupt change of the object to be
tested from 80% of the tripping value to 120% of the tripping value.
If the User is testing tripping delays of „less than“ modules (e.g.: P<), start
a timer simultaneously with an abrupt change of the object to be tested
from 120% of the tripping value to 80% of the tripping value.
www.eaton.com
694
Содержание EDR-5000
Страница 63: ...EDR 5000 IM02602007E Ethernet RJ45 Terminal Marking www eaton com 63 1 8 TxD TxD RxD N C N C RxD N C N C...
Страница 253: ...EDR 5000 IM02602007E Fault Recorder Module Signals Signal Description Res record Signal Delete Record www eaton com 253...
Страница 887: ...EDR 5000 IM02602007E Real Time Clock Running Reserve of the Real Time Clock 1 year min www eaton com 887...