Step 7 - Check terminations, secure cables and test insulation
1
Check all terminations are correct and are tightened.
2
Tighten the ac cable entry gland to ensure there is no strain on the terminals.
Secure the cable with cable ties.
3
Replace the ac MCB cover or ac terminal cover.
4
Test the insulation resistance of the conductors according to local ac wiring
regulations.
Procedure complete
Task 4 - Mount the APS in the Rack
Step 1 - Check clearances
APSs require the following minimum clearances:
Front Clearance - 600mm (24") for access and unrestricted air intake.
Rear Clearance - 50mm (2”) from back of rack, other equipment and cables to
allow air escape route for optimum system cooling.
Top Clearance - 1U (44.45mm / 1¾") minimum from other equipment in the
rack. Recommended for access to cable terminations.
Step 2 - Fit cage nuts
Fit cage nuts in the correct positions to match the screw holes in the APS rack
mounting brackets.