Access Power Solutions Installation and Operation Guide (APS6-300/500 and APS12-300 Series)
40
Copyright © 2007-2013 Eaton Corporation. All Rights Reserved.
IPN 997-00012-49G May 2013
Step 4 - Check the rectifier currents
1
Check the rectifier currents.
2
Verify the load current is as expected for the load and battery size and
does not exceed the maximum load rating (see details on page
Step 5 - Charge the batteries
1
Charge the batteries according to the battery manufacturer’s
recommendations.
2
If an Equalize charge is recommended by the battery manufacturer then
follow the instructions.
Equalize increases the system voltage to the Equalize voltage for the
Equalize duration. After the Equalize duration has expired, the dc power
system voltage reverts to float voltage automatically.
Procedure complete
Start-Up Completed
Start-Up of the APS is now complete and the system is operational.
If a formal commissioning test is required then see the Commissioning check lists on page
The System Controller Operation Handbook (see Related Information on page
) describes how
to use the SC200 or SC100 system controller. See:
System Operation
to customize the system configuration settings, and
Communications
to setup the remote communications options.
For information on alarms, or operation problems see Maintenance on page