Start-Up
Copyright © 2007-2013 Eaton Corporation. All Rights Reserved.
IPN 997-00012-49G May 2013
39
Parameter
Action
Where to find
Temperature
Compensation
Enable (if battery and
battery temperature
sensor connected) and
check the settings.
SC100:
Menu > Configuration > Temp
Compensation > Edit
SC200:
Control Processes > Temp. Compensation >
Enable
DCTools:
Control Processes > Temperature
Compensation
Low Voltage
Disconnect
(LVD)
Enable (if LVD(s) installed
and battery connected)
and check the settings.
SC100:
Menu > Configuration > LVD1/LVD2
SC200:
Battery > LVDs > LVD x
DCTools:
Control Processes > LVD
System controller
time (SC200
only)
Connect using Web to set
correct time manually or
connect using DCTools to
synchronize to PC time.
See details in the System
Controller Operation
Handbook.
Web:
Configuration > Time
DCTools:
Configuration > Time > Time
Synchronization
Task 5 - Applying DC Power to Battery and Load
Reverse Polarity
Always check that the battery cables have been terminated to the correct system polarity BEFORE
connecting the batteries or closing the battery disconnect device. Connecting batteries to the dc power
system with incorrect system polarity will damage the rectifiers and void all warranty claims.
Step 1 - Check dc voltage and polarity
Check the dc output voltage and polarity of the power system and the
battery string(s).
Step 2 - Connect batteries
1
If connecting multiple battery strings then check the individual strings
are of similar voltage.
2
Switch on all Battery MCB(s) and/or fit the battery fuses.
3
Check the Battery Fuse Fail alarm clears.
All Battery MCBs (including any unused MCBs) must be switched on
to clear the alarm.
4
Check the battery current. The actual value depends on the state of
charge of the batteries.
Step 3 - Connect load
1
Switch on the Load MCB(s) and/or fit the Load fuses.
2
Check the equipment powers up and the Load Fuse Fail alarm clears.