Commissioning
Copyright © 2007-2013 Eaton Corporation. All Rights Reserved.
IPN 997-00012-49G May 2013
103
Digital Outputs (Relays)
Test
Test procedure
Adjustment
Digital Output 1
Note 1
Refer to
Digital Outputs
in the SC200 or SC100 handbook.
Follow the instructions to manually change the state of the
digital output.
When the digital output is
Active,
check any remote alarms
are extended.
When the digital output is
Inactive,
check any remote
alarms are return to their original state.
Digital Output 2
As for Digital Output 1.
Digital Output 3
As for Digital Output 1.
Digital Output 4
As for Digital Output 1.
Digital Output 5
As for Digital Output 1.
Digital Output 6
Note 2
As for Digital Output 1.
User assigned
Digital Outputs
As for Digital Output 1.
Notes
1
Digital Outputs can also be checked as other system tests are performed.
2
Digital Output 6 is also used as the Monitor Fail alarm relay. It will de-energize if the I/O
board loses power or loses communication with the SC200 or SC100. Test extended alarms
by removing the power to the I/O board. This will de-energize the relay.
Commissioning Completed
Restore the original (backed-up prior to the testing) configuration file.
Use DCTools/Web to change any configuration file settings that were noted as incorrect during
the Commissioning tests.