![DSEGenset DSE8610 Скачать руководство пользователя страница 77](http://html1.mh-extra.com/html/dsegenset/dse8610/dse8610_operators-manual_2535081077.webp)
Operation
77
6.2.2 LOAD SHEDDING CONTROL
The
Load Shedding Control
feature (if enabled) allows for a maximum of five load-shedding steps.
When the generator is about to take load, the configured number of
Load Shedding Control Outputs at
Startup
will energise. This configurable setting allows (for instance) certain loads to be removed from
the generator prior to the set’s load switch being closed. This can be used to ensure the initial loading
of the set is kept to a minimum, below the
Load Acceptance
specification of the generating set.
The generator is then placed on load. The
Load Shedding Control
scheme begins.
When the load reaches the
Load Shedding Trip
level, the
Trip Delay
timer will start. If the generator
loading is still high when the timer expires, the first
Load shedding Control
output will energise. When
the load has been above the trip level for the duration of the timer the ‘next’
Load shedding Control
output will energise and so on until all
Load Shedding Control outputs are energised.
If at any time the load falls back below the
Load Shedding Return
level, the
Return Time
will start. If
the load remains below the return level when the timer has expired the ‘highest’
Load Shedding
Control
output that has been energised will be de-energised. This process will continue until all outputs
have been de-energised.
When the set enters a stopping sequence for any reason the
Load Shedding control
’ outputs will de-
energise at the same time as the generator load switch is signalled to open.
Example screen shot of
Load Shedding Control
setup in the DSE Configuration Suite
Содержание DSE8610
Страница 47: ...Installation 47 4 2 2 3 PHASE 4 WIRE WITHOUT EARTH FAULT PROTECTION...
Страница 51: ...Installation 51 4 3 2 SINGLE PHASE WITHOUT EARTH FAULT...
Страница 53: ...Installation 53 4 3 4 2 PHASE L1 L2 3 WIRE WITHOUT EARTH FAULT...
Страница 55: ...Installation 55 4 3 6 2 PHASE L1 L3 3 WIRE WITHOUT EARTH FAULT MEASURING...
Страница 100: ...Protections 100 8 8 1 EARTH FAULT TRIPPING CURVES NOTE DSE Factory setting is time multiplier K 0 4...
Страница 118: ...Intentionally Left Blank 118...