VP5000-DC/DC60, VP5000-DC/DC200-HL
Notes on planning
Last edited 2019-02-08
by Sonja Scheunert
Filename
VP5000_DCDC60_200-HL_installation_manual_v1-4en.docx
81 / 173
4
Notes on planning
Qualification of the planner
4.1
Hardware planning for integration into a system may only be carried out by a qualified electrician
as defined in this manual. See chapter 2.7.1 Safety, Personnel requirements, Qualified electrician.
Software planning for integration into a system may only be carried out by a programmer as
defined in this manual. See Chapter 2.7.2 Safety, Personnel requirements, Programmer.
Checklist for system integration of the VECTOPOWER
4.2
The following checklist gives the requirements that are generally considered during system
integration. Other requirements may apply for your specific application. Check this checklist and
add any additional requirements necessary for your application.
Take the following into account when planning the system
For further information see
chapter
General principles:
Standards, directives, and statutory provisions
Minimizing residual risks, creating safety
Scenarios for project planning
Project engineering manual
VP600 / VP5000, chapter
Overview of application
scenarios
In the design:
Performance data, current and voltage limits
3.3.1, 3.3.2, 3.3.3, 3.3.5,
3.3.7, 3.9, 3.10, 3.11
Operating conditions (environment)
Derating
Wires and cable glands
During the integration of the hardware
Installation position
Space required for connections
Hot surfaces:
- Space for air circulation and
- Protection against accidental contact
Operating noises:
- Soundproofing measures
Secure fastening:
- Mounting plate must be load-bearing
- Screw connection must be secured
IP protection class
EMC measures:
4.3.18, Manual for project