HVC-R 100/150 E-Bus Charger Installation Guide
Document: v0.4 / Document No.: TBA | Date: 11-08-2021 Page
59
of
131
5.5. Installing the Power Cabinet onto a foundation
5.5.1. Connecting Power Cabinet to a foundation
Prerequisites:
Tools: spanner (size 24).
Cover caps (4x) that were removed from the Power Cabinet (bag with parts).
The Power Cabinet is about 500 mm above its location.
DANGER
Make sure that the main switch of the power supply group for the product
is set to the
OFF
position.
Do a voltage check
to make sure that the
electrical power is disconnected from the system. Secure against
resetting.
WARNING
Make sure that personnel cannot be crushed or become trapped while
moving the Power Cabinet.
Placing the Power Cabinet on concrete foundation
A
Foundation
B
Power Cabinet
C
Cables
D
Tapped holes
Содержание HVC-R 100
Страница 1: ... INSTALLATION GUIDE HVC R 100 150 E Bus Charger Installation Guide for EU products Version 0 4 ...
Страница 122: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 122 of 131 ...
Страница 125: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 125 of 131 ...
Страница 131: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 131 of 131 NOTES ...