HVC-R 100/150 E-Bus Charger Installation Guide
Document: v0.4 / Document No.: TBA | Date: 11-08-2021 Page
35
of
131
Example of civil installation when the Dual Depot Charge Box is mounted on the pedestal
A
Foundation of the Power Cabinet
B
Foundation of the Dual Depot Charge Box
C
Flexible conduit for DC power cables
D
Flexible conduit for AC auxiliary power, PE wire and data cables
E
AC power cable for the Power Cabinet
Example of civil installation when the Dual Depot Charge Box is mounted on a wall
A
Foundation of the Power Cabinet
B
Wall on which the Dual Depot Charge Box will be mounted
C
Flexible conduit for DC power cables
D
Flexible conduit for AC auxiliary power, PE wire and data cables
E
AC power cable for Power Cabinet
NOTICE
Document the location of all the cables placed in the ground between the
Power Cabinet and the Dual Depot Charge Box. The routing of the cables
must be known to prevent damage caused, e.g. by excavation works.
Содержание HVC-R 100
Страница 1: ... INSTALLATION GUIDE HVC R 100 150 E Bus Charger Installation Guide for EU products Version 0 4 ...
Страница 122: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 122 of 131 ...
Страница 125: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 125 of 131 ...
Страница 131: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 131 of 131 NOTES ...