3.2. About preparation
The planning steps for the preparation phase are shown in the figure below:
Diagram of preparation phase’s steps
A1
Ordering
Order the HVC-R 100/150 E-Bus Charger.
A2
Engineering
The Owner / Site Operator selects a Contractor to perform the civil and electrical
installation works. The Contractor is responsible for all construction documentation of
the site, i.a.: drawings, calculations, certifications, licenses and test reports.
The location of the HVC-R 100/150 E-Bus Charger must be selected. See section
Location
on Page 27 and section
Geometry of infrastructure
on Page 28.
A3
Get permits
Make sure that all the permits required by local regulations had been acquired.
See section
Required permits
on Page 24.
A4
Upgrade grid
If required, upgrade the electrical grid connection to 3-phase 400 V AC. See section
Adapting the grid
on Page 26.
A5
Transport foundation(s) on request
If it is necessary to order the foundation(s), transport of the foundation(s) must be
arranged with the ABB Delivery department. See
Contact information
on Page 12 for
contact.
Содержание HVC-R 100
Страница 1: ... INSTALLATION GUIDE HVC R 100 150 E Bus Charger Installation Guide for EU products Version 0 4 ...
Страница 122: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 122 of 131 ...
Страница 125: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 125 of 131 ...
Страница 131: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 131 of 131 NOTES ...