HVC-R 100/150 E-Bus Charger Installation Guide
Document: v0.4 / Document No.: TBA | Date: 11-08-2021 Page
37
of
131
4.
Construction
4.1. About construction
The construction phase includes all works required to prepare the location and make it ready
for the placement and connection of the HVC-R 100/150 E-Bus Charger. The construction
phase can start when:
All engineering work is done.
All permits are granted.
The grid connection is available.
The planning steps for the construction phase are shown in the figure below:
Indication of Construction phase on the planning diagram
B1
Civil engineering works
Construction of the foundation - see section
Providing foundation for the Power
Cabinet
on Page 38 and section
Mounting of the Dual Depot Charge Box
on Page 43.
Installation of the cable connections - see section
Cable routing
on Page 46.
Construction of the bus stop surrounding - see section
Geometry of infrastructure
on
Page 28.
B2
Electrical engineering works
See section
Electrical installation
on Page 33 and section
Adapting the grid
on Page
26.
B3
Internet access (optional)
This step can be ignored if the location has sufficient 3G coverage. Otherwise, an
Ethernet (RJ45) connection has to be installed - see section
Internet connection
on
Page 51.
Содержание HVC-R 100
Страница 1: ... INSTALLATION GUIDE HVC R 100 150 E Bus Charger Installation Guide for EU products Version 0 4 ...
Страница 122: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 122 of 131 ...
Страница 125: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 125 of 131 ...
Страница 131: ...HVC R 100 150 E Bus Charger Installation Guide Document v0 4 Document No TBA Date 11 08 2021 Page 131 of 131 NOTES ...