COMMISSIONING CHECKLIST (CONTINUED)
10.
Ensure System and Zone Tests perform satisfactorily.
11.
Verify the programming, wiring and operation of the system.
Ie Check for each zone:
a)
Alarm and fault conditions can be generated.
b)
The alarm delay is as the input type. Ie Normal, AVF, 1668 or Flow Switch.
c)
The zone is enabled and latching or non-latching as required.
d)
The appropriate outputs (Ancillary Relay, Auxiliary, Brigade and bells) operate
as programmed or wired.
e)
The Ancillary Relay supervision detects open and short circuit faults, if it is
enabled.