Document No: LT0082
F08 Installation & Programming Manual
Placing
into
Operation
POWER UP (CONTINUED)
STEP 7
:
Perform a Battery Test.
(a)
Select Battery/Charger ( By pressing SELECT until the Battery/Charger "SEL"
indicator is illuminated).
(b)
Press the key once.
-
The Battery/Charger "SEL" indicator will flash to indicate a battery test
is in progress.
TEST
-
The test will take 1 minute to complete.
(c)
If the Battery test fails the amber "FLT" LED indicator will flash;
i.
Check battery connections;
ii.
If the battery is flat, leave on charge for 24 hours and retest.
iii.
Check Battery Low Monitoring circuit for correct operation.
STEP 8
:
Perform an MCP test.
(a)
Insert the plastic MCP test key into the MCP for a period of 2 to 3 seconds.
(b)
The zone that the MCP is wired to should indicate an alarm by flashing its
"ALARM" LED and any programmed outputs should operate.
(c)
Press the key once to clear the ALARM.
(d)
Disconnect a wire at the MCP.
RESET
(e)
The zone that the MCP is wired to should indicate a fault by a steady "FLT"
LED.
(f)
Re-connect the wire to the MCP.
(g)
Press the SELECT key until the MCP zone is selected.
Press the key once to clear the FAULT.
RESET
Issue 3.04
24 March 2006
Page 3-5